Project Overview Sewer System Improvements
Project will consist of rehabilitating defects in the sanitary sewer collection system that are identified in the FY22 sanitary sewer evaluation survey (SSES) Project. Potential rehabilitation efforts will include cured-in-place pipe (CIPP) lining, manhole rehabilitation and miscellaneous point repairs. The project is part of the City of Auburn's <a href="">Other</a>.
The project was completed on Jun 20, 2025 with a total capital budget of $990,611.28.
Photos




Timeline
Aug 2025
Close Out Finishes
Aug 15, 2025
Jun 2025
Close Out Starts
Jun 21, 2025
Jun 2025
Construction Finishes
Jun 20, 2025
Oct 2024
Construction Starts
Oct 15, 2024
Aug 2024
Contracts Finishes
Aug 4, 2024
Jul 2024
City Council / AWWB Starts
Jul 16, 2024
Jul 2024
Contracts Starts
Jul 16, 2024
Jun 2024
Bid Opening Starts
Jun 27, 2024
Jun 2024
Bid Advertisement Finishes
Jun 27, 2024
Jun 2024
Bid Advertisement Starts
Jun 1, 2024
May 2024
Design Finishes
May 31, 2024
Oct 2023
Design Starts
Oct 1, 2023